Company name |
Metal Heat Co., Ltd. | |
---|---|---|
Locations | Headquarters Second plant Mie business office |
5-3-6 Toei-cho, Anjo-city, Aichi, 446-0007, JAPAN 6-1-1 Toei-cho, Anjo-city, Aichi, 446-0007, JAPAN 1075-9 Hattanda, Higashiyuriage, Kuwana-city, Mie Prefecture, 511-0806, JAPAN |
Tel | +81-566-98-2501 | |
Fax | +81-566-98-2504 | |
Company's website |
http://www.metalheat.co.jp/english/ | |
Established | 1973 | |
Capital | \10 million | |
Representative Director | Toshiki Hara | |
Employees | About 50 employees | |
Banks | The Bank of Tokyo-Mitsubishi UFJ, Ltd. Anjo branch The Hekikai Shinkin Bank Imamura branch The Juroku Bank, Ltd. Okazaki branch The Ogaki Kyoritsu Bank, Ltd. Anjo branch |
|
Plant site area | 7,102 ㎡ | |
Plant building area |
3,277㎡ | |
International standards | ISO 9001:2008 ISO 14001:2004 (Certified on March, 2006) |
|
Associate companies |
Metal Heat Engineering Co., Ltd. | |
Organizations | Japan Metal Heat Treatment Association Chubu Metal Heat Treatment Association The Japan Society for Heat Treatment Aichi Small Business Support Center Anjo Chamber of Commerce and Industry G-Interactive |
Over 40 years of history: Specialized in vacuum heat treatment
Specialized in vacuum heat treatment over 40 years since 1973.
We can satisfy the needs of our customers with years of experience and our original heat treating techniques.
1973 | Established |
---|---|
1989 | Super large vacuum heat treatment furnace was introduced. |
1991 | Wire cutting plant was built (15 WEDM machines). |
2005 | The new HQ was built and the plant was moved to the current location. |
2007 | Environmental section was newly founded. |
2012 | The second plant was built. Continuous hydrogen atmosphere furnace was introduced. Large vacuum heat treatment furnace was introduced. The number of heat treatment furnaces reaches 17. |
2013 | One large vacuum heat treatment furnaces were introduced. (V18 furnace) |
2014 | Two large vacuum heat treatment furnaces are scheduled to be introduced. (V19 furnace, V20 furnace) |
[By railway] ●Approx. 10-minute walk from Shin-Anjō Station on Meitetsu Railway. ●Approx. 10 minutes by taxi from Anjō Station on JR. ●Approx. 15 minutes by taxi from Mikawa-Anjō Station on JR Shinkansen Line. [By car] ●From Tōmei Expressway Take Okazaki Exit on Tōmei Expressway and turn towards Nagoya on the National Highway Route 1. Approx. 300m from the Toei-cho intersection on the left side (along the Route 1). Approx. 22 minutes from Okazaki Exit. ●From Isewangan Expressway Take Toyota-Minami Exit on Isewangan Expressway. Turn left on the National Highway Route 1 towards Okazaki (along the Route 1). Approx. 17 minutes from Toyota-Minami Exit. |